by prestwichfocus on 25 February, 2014
Work to expand park and ride facilities at Radcliffe Metrolink stop will begin on Monday 3 March. This will take about five months, during which time the number of spaces will be reduced from 250 to around 70.
As you may know, parking at Whitefield Metrolink is currently suspended while similar work, expected to be completed in the summer, is carried out.
We’re not quite sure why work on both car parks has to take place at the same time, and we would be grateful if you could get in touch if this is causing parking problems around the Metrolink stations nearer here.
For more details, and news about the closure of Victoria station and alternative routes, go to http://www.metrolink.co.uk/Pages/default.aspx